RFQs & suppliers
How to Spot Scope Gaps in Electrical Supplier Quotes
Check supplier inclusions and exclusions against the tender scope, price missing work and keep unresolved items visible before closing.
3 min read
Illustrative photograph by Valentin Ivantsov, used under the Pexels License.
A supplier can quote every piece of equipment on the schedule and still leave required work out of our number. A lighting controls quote might include the sensors, switches and control panels while excluding programming and start-up. The equipment count could be right, but we still need to find out who will do that work and what it will cost.
Example notice: Project scenarios and pricing examples created for these articles are fictional and for educational use only. Amounts are in Canadian dollars.
Check what the job requires
Start with the issued drawings, specifications and addenda. For a lighting controls package, check who supplies the devices, who installs and connects them, and who handles programming, start-up and testing. Keep those tasks separate. For example, a quote that includes one start-up visit may still leave programming or functional testing to someone else.
Then read the supplier’s inclusions, exclusions and notes against those requirements. Mark each item as included, excluded or unclear. If the quote is silent about programming, mark it unclear and ask the supplier. If the quote explicitly excludes programming, assign the work to whoever will perform it and get a price.
Public Services and Procurement Canada advises federal bidders to review the statement of work, mandatory requirements and pricing structure for each solicitation. Apply the same discipline to the supplier review, using the documents and instructions issued for your tender. Preparing to bid on an opportunity.
Compare the cost of covering the same work
Suppose the specification requires programming and one on-site start-up visit. Both suppliers offer equipment that meets the tender requirements, with the same quantities and delivery terms.
| Scope | Supplier A | Supplier B |
|---|---|---|
| Equipment package as quoted | $12,800 | $14,100 |
| Programming and one on-site start-up visit | Excluded | Included in the quoted price |
| Separate written price for the excluded work | $1,600 | Already included |
| Comparable cost before tax | $14,400 | $14,100 |
Supplier A’s equipment quote is $1,300 lower. Once we add the separately priced service, Supplier B is $300 lower for the scope shown.
Keep Supplier A’s original quote at $12,800 in the estimate record. Show the $1,600 service quote separately so the reviewer can see who priced the work. Before using that amount, confirm that the service provider can program the equipment offered by Supplier A and perform the visit within the required schedule.
Keep unclear scope visible before closing
A useful supplier question names the exact work that needs an answer. For example, ask whether the quoted total includes programming all lighting control zones shown on the issued drawings and one on-site start-up visit. If either item is excluded, request a written price and confirm what the electrical contractor must have ready before the visit.
If the supplier replies “start-up included” and says nothing about programming, keep programming open. Record who is following up, when the answer is needed and which amount is currently carried in our number. If the estimator uses an approved internal allowance, record its basis separately from the supplier quote and keep supplier confirmation outstanding. Follow the tender instructions when deciding how to proceed with any unresolved item.
Before releasing our quote, check that every required task has someone assigned to do it and a checked cost in the estimate. If programming is in the supplier package, check that we haven’t carried it again in a separate service line. If it’s excluded, check that the separate cost made it into the bid total.
General estimating workflow guidance. Project requirements and contractual documents take precedence; this is not electrical design or code-compliance advice.